Objective: Comparison of Earthwork volume between MiTS 1 and MiTS 2
There are few parameters that we will keep constant to reduce the discrepancy between each project file. The parameters are listed as follow:
- Using TIN as meshing method
- Grid size
- Angle: 0
- Interval: 5m
- Left offset: 2.5m
- Right offset: 2.5m
- End-Area
- Interval: 5m
With slope #
Swell/Shrink Factor: 1.00
You can refer to the MiTS 1 project file here.
You can refer to the MiTS 2 project file here.
Method | MiTS 1 | MiTS 2 | Discrepancy |
DTM | 476638.77 | 474631.90 | 0.42% |
Grid | 362866.72 | 476171.18 | 27.01% |
End-Area | 476771.49 | 474752.40 | 0.42% |
Without slope #
Swell/Shrink Factor: 1.00
You can refer to the MiTS 1 project file here.
You can refer to the MiTS 2 project file here.
Method | MiTS 1 | MiTS 2 | Discrepancy |
DTM | 358365.46 | 358366.66 | 0.00% |
Grid | 362866.72 | 360416.96 | 0.68% |
End-Area | 357810.16 | 357811.73 | 0.00% |
With shrink/swell factor (with slope) #
Swell/Shrink Factor: 0.70
You can refer to the MiTS 1 project file here.
You can refer to the MiTS 2 project file here.
Method | MiTS 1 | MiTS 2 | Discrepancy |
DTM | 273396.60 | 271994.63 | 0.51% |
Grid | 218282.41 | 274146.18 | 22.69% |
End-Area | 273547.74 | 272132.50 | 0.52% |
Note: You can refer here to know the detailed earthwork computation for a project with shrink/swell factor.
Conclusion #
In conclusion, for DEM and End-Area Method, the results obtained from MiTS 1 and MiTS 2 typically show a little discrepancy of less than 1%, which can be attributed to algorithmic improvements made in MiTS 2. Whereas for Grid Method, there are significant differences between the results obtained in MiTS 1 and MiTS 2. This happens because one limitation of the Grid Method used in MiTS 1 is that it does not account for the effects of slope, resulting in identical EW volumes regardless of slope information. However, this limitation has been fixed and improved in MiTS 2.