603 - 5885 1250 (4 lines) info@mes100.com

(MiTS 2.0.51.0 onwards)

Existing Road

To change the gradient of carriageway, shoulder and verge of existing road, go to:

i. Carriageway

Super-elevation > Spread Input > Adjust Cross Slope Rate % value

image1

ii.  Shoulder

Road Width > Properties tab on RHS > Adjust Shoulder Cross Slope,% value  

image6

iii.  Verge

Options > Project Parameters > Road > Analysis > Design > Verge Slope, % (Adjust  

the value)

* Verge slope gradient is calculated independently if “Verge & shoulder Slope Independent” is ticked. If it is unticked, verge slope is calculated cumulatively from shoulder slope. Calculation of the gradient can be referred in the spreadsheet. Click Here.

image2

New Road

All values set in the Parameter will be applied towards new road design.