Table of Contents
Parameter Setting #
The parameter of MiTS-Clash Analysis can be set.
Options > Project Settings > Expand Clash Analysis
Collision Detection #
Consists of parameter settings for (1) Minimum Vertical and Horizontal Clearance and (2) Clash Sign Position.
- Minimum Vertical and Horizontal Clearance => The minimum vertical and horizontal distance between the drain, sewerage pipe and water reticulation pipe.
- Clash Sign Position => The position of the Warning / Clashing sign above the pipes and drains in the Long Sections.

AutoAdjust #

Layers #

Clash Analysis #
Before proceeding to clash analysis, make sure at least two of the networks (drainage, sewerage, and/or water ret.) passed the analysis.
This can be checked under ‘Utility Status’ on the RHS Panel.