Table of Contents
Parameter Setting #
The parameter of MiTS-Clash Analysis can be set.
Options > Project Settings > Expand Clash Analysis
Collision Detection #
Consists of parameter settings for (1) Minimum Vertical and Horizontal Clearance and (2) Clash Sign Position.
- Minimum Vertical and Horizontal Clearance => The minimum vertical and horizontal distance between the drain, sewerage pipe and water reticulation pipe.
- Clash Sign Position => The position of the Warning / Clashing sign above the pipes and drains in the Long Sections.
![](https://i0.wp.com/mes100.com/wp-content/uploads/2024/07/image2-2.png?resize=957%2C632&ssl=1)
AutoAdjust #
![](https://i0.wp.com/mes100.com/wp-content/uploads/2024/07/image3-2.png?resize=946%2C632&ssl=1)
Layers #
![](https://i0.wp.com/mes100.com/wp-content/uploads/2024/07/image4-1.png?resize=943%2C623&ssl=1)
Clash Analysis #
Before proceeding to clash analysis, make sure at least two of the networks (drainage, sewerage, and/or water ret.) passed the analysis.
This can be checked under ‘Utility Status’ on the RHS Panel.
![](https://i0.wp.com/mes100.com/wp-content/uploads/2024/07/image1-2.png?resize=1024%2C545&ssl=1)