by Ngu Soon Hui | Feb 2, 2018 | Blog, MiTS 1, Troubleshooting/Tips
If users encounter such error shown below, you may follow the following steps to encounter the problem. Steps: Open project > Analyze > Click on 3D View Error message shown in Image 1 pops up Image 1 Error message pops up when generating 3D View Solution: Click...
by Ngu Soon Hui | Dec 7, 2017 | Blog, MiTS 1, Technical Documentation
(This is already outdated; please refer to our user guide for the latest information) CLASH ANALYSIS Purpose : To check the clash between drainage, water reticulation and sewerage 1.0 Clash Analysis Make sure analysis of at least two of the networks has passed...
by Ngu Soon Hui | Dec 5, 2017 | Blog, MiTS 1, Troubleshooting/Tips
1.0 Issue (between platform) Longer berm is at the top instead at the bottom which may cause failure in construction due to inadequate support to carry the load at the bottom. Image 1 Full berm is located at the above part 1.1 How Does It Happen Project reference :...
by Ngu Soon Hui | Nov 15, 2017 | Blog, MiTS 1, Troubleshooting/Tips
How to create platform for retaining wall Image 1 *not drawn in scale Project reference : EW3D 1.0 Issue Retaining wall and slope are needed to be constructed between two platforms as shown in Image 1. Reference as in the project attached, it is situated between...
by Ngu Soon Hui | Nov 1, 2017 | Blog, MiTS 1, Technical Documentation
There are some changes in MiTS 3 when it comes to the calculation of the verge slope ratio MiTS 1/MES Module: Road Go to: > Cross Section Detailing As shown above, the verge slope is 1:3.4. Go to: Options >> Parameters >> Analysis >> Design As stated above, the verge...
by Ngu Soon Hui | Jul 19, 2017 | Blog, MiTS 1, Troubleshooting/Tips
This is a file system limitation problem. Kindly follow below steps to solve this problem 1. You will need to delete file and folder; error.txt and error folder 2. Search %appdata% >> MES Innovation Sdn Bhd >> LoopWinPlus >> error.txt...