Normally, the contractor will provide as-built drawing for Earthwork progress and C&S engineer will be required to check the EW volume submitted by the contractor.

In MiTS, the as-built comparison with OGL can be done by comparing the two (2) sets of survey points imported as a whole area (by convex hull) or by comparing by boundary area.  

In this documentation, we do comparison results between DTM and End Area for EW Volume based on a boundary.

  EW Volume based on Zone (Boundary)
DTM

 

 

EW Volume calculate based on convex hull area between OGL and As Built

End Area

EW Volume calculate based on ‘Average End Areas’ method

Zone 1 Result

EW Volume = Cut – fill

From the image above (DTM result),

Zone 1 EW Volume = 215.26 m3 – 1188.94 m3 = -973.68 m3

Zone 2 Result

EW Volume = Cut – fill

From the image above (DTM result),

Zone 1 EW Volume = 844.65 m3 – 199.80 m3 = 644.85 m3

Zone 3 Result

EW Volume = Cut – fill

From image above (DTM result),

Zone 1 EW Volume = 171.72 m3 – 5.53 m3 = 166.19 m3

 

We would say that the EW volume calculated may not be exactly the same between methods used and may have 2% – 4% discrepancies. For further explanation user may refer ‘The DTM method and accuracy of MiTS 2 Earthwork” here